Chisholm & Winch has successfully installed the final passive fire protection (PFP) board to the crown of the Heathrow Cargo Tunnel, connecting Terminals 3 and 4, for delivery partner Mace. This milestone marks a significant achievement in the refurbishment project, with a total of 11,000 boards installed in the 860m tunnel.
The Cargo Tunnel refurbishment project began in Q1 of 2022 and is scheduled for completion by June/July 2025. The dedication and hard work of our team over the past two and a half years, working under challenging conditions, has been instrumental in reaching this latest milestone.
Chisholm & Winch maintained an average workforce of 40 individuals on the project, peaking at 65 during the most demanding phases. Work has been carried out at night to keep the tunnel operational during the day. The tunnel is closed each night at 9 pm, and our team, using 10 MEWPs (mobile elevated work platforms), begins work by 9.30 pm. Coordination with other trades working simultaneously in the tunnel is critical to avoid delays.
Daily operations are meticulously planned and reviewed. Each morning, a wash-up meeting with stakeholders reviews the previous night’s progress, followed by a pre-plan NABS meeting for the upcoming night’s work. The teams use DataTouch, an interactive project planning software, to manage various aspects of the project, helping to avoid conflict with other companies by blocking out specific work locations for Chisholm & Winch.
As the project builder, after completing the ceiling PFP installation, our scope of works includes concreting, installing bases for the fans, painting plant rooms, installing new services such as electrics and lighting, and boxing the services with fire cladding.
Reaching this major milestone underscores the hard work of our team and paves the way for the project’s remaining phases, ensuring completion by mid-2025.